Saturday, March 22, 2008

United States Department of Defense - C-17 Globemaster III


The Boeing (formerly McDonnell Douglas) C-17 Globemaster III is an American strategic airlifter manufactured by Boeing Integrated Defense Systems, and operated by the United States Air Force, British Royal Air Force, the Royal Australian Air Force, and the Canadian Forces Air Command. NATO also has plans to acquire the airlifter.

The C-17 Globemaster III is capable of rapid strategic delivery of troops and all types of cargo to main operating bases or directly to forward bases in the deployment area. It is also capable of performing tactical airlift, medical evacuation and airdrop missions. The C-17 takes its name from two previous United States cargo aircraft, the C-74 Globemaster and the C-124 Globemaster II.

In the 1970s, the US Air Force began looking for a replacement for the C-130 Hercules tactical airlifter. The Advanced Medium STOL Transport (AMST) competition was held, with Boeing proposing the YC-14, and McDonnell Douglas proposing the YC-15. Despite both entrants exceeding specified requirements, the AMST competition was canceled before a winner had been selected.

By the early 1980s, the USAF found itself with a large fleet of aging C-141 Starlifter cargo aircraft. Some of the C-141s had major structural problems due to heavy use. Compounding matters, USAF historically never possessed sufficient strategic airlift capabilities to fulfill its airlift requirements. In response, McDonnell Douglas elected to develop a new aircraft using the YC-15 as the basis. McDonnell Douglas was awarded a contract to build its proposed aircraft, by then designated the C-17A Globemaster III, on August 28, 1981. The new aircraft differed in having swept wings, increased size, and more powerful engines. This would allow it to perform all work performed by the C-141, but to also fulfill some of the duties of the C-5 Galaxy, freeing the C-5 fleet for larger outsize cargo.

Development continued until December 1985 when a full-scale production contract was signed for 210 aircraft. Development problems and limited funding caused delays in the late 1980s. Questions were also raised about more cost-effective alternatives during this time. In April 1990, Defense Secretary Richard Cheney reduced the order from 210 to 120 aircraft. The C-17's maiden flight was on September 15, 1991 from the McDonnell Douglas west coast plant in Long Beach, California, about a year behind schedule. This aircraft (T-1) and five more production models (P1-P5) participated in extensive flight testing and evaluation at Edwards AFB. In late 1993, the DoD gave the contractor two years to solve production and cost overrun problems or face termination of the contract after the delivery of the fortieth aircraft. By accepting the 1993 terms, McDonnell Douglas incurred a loss of nearly US$1.5 billion on the development phase of the program.

In April 1994, the C-17 program was still experiencing cost overruns, and did not meet weight, fuel burn, payload and range specifications. Airflow issues caused problems with parachutes and there were various other technical problems with mission software, landing gear, etc.A July 1994 GAO document revealed that to justify investing in the C-17 rather than in the C-5, Air Force and DoD studies from 1986 and 1991 had claimed that the C-17 could use 6,400 more runways (outside the US) than the C-5. It was later discovered that this study had only considered the runway dimensions, but not their strength or Load Classification Numbers (LCN). The C-5 has a lower LCN than the C-17, although the US Air Force places both in the same broad Load Classification Group (LCG). When considering runway dimensions and their load ratings, the C-17's worldwide runway advantage over the C-5 shrank from 6,400 to 911 airfields.However, the C-17's ability to use lower quality, austere airfields was not considered.

A January 1995 GAO report revealed that while the original C-17 budget was US$41.8 billion for 210 aircraft, the 120 aircraft already ordered at that point had already cost US$39.5 billion. In March 1994, the U.S. Army had decided it no longer needed the 60,000 lb (27,000 kg) Low Altitude Parachute Extraction System (LAPES) delivery that the C-17 was supposed to provide, feeling that the 42,000 lb (19,000 kg) capability of the C-130 Hercules was sufficient. It was decided not to conduct C-17 LAPES training beyond the testing of a 42,000 lb (19,000 kg) LAPES delivery. There were still airflow problems making it impossible for the C-17 to meet its original airdrop requirements. A February 1997 GAO Report revealed that a C-17 with a full payload could not land on 3,000 feet (900 m) wet runways, for simulations suggested 5,000 ft (1,500 m) was required.

By the mid-1990s, most of the problems had been resolved. The first C-17 squadron was declared operational by the U.S. Air Force in January 1995. In 1996, DoD ordered another 80 aircraft for a total of 120. In 1997 McDonnell Douglas merged with its former competitor, Boeing. In 1998, the order was increased to 134 units and in August 2002 to 180.

In July 2006, C-17A production was planned to end in 2009 unless Boeing received a follow-on order in sufficient time to allow the production pipeline to remain in operation. If such an order is placed, Boeing would begin C-17B production in 2010. The proposed C-17B would be capable of landing on sandy beaches and other areas off-limits to the C-17A.

On August 18, 2006 Boeing announced it was telling suppliers to stop work on parts for uncommitted C-17s. This move is the first step in shutting down production if no new plane orders were received from the US Government. However, just one month later on September 21, a House and Senate conference committee approved a US$447 billion defense bill for 2007, that includes US$2.1 billion for 10 additional C-17s – which is seven more planes than either chamber originally approved in separate versions of their funding language. The additional purchase follows intense lobbying by Boeing, as well as by California state leaders (where the plane is manufactured), and Missouri leaders, where Boeing's defense business is based. However, this extends the life of the program for only one additional year, to 2010.

On March 2, 2007, Boeing announced the C-17 production line may end in mid-2009 due to the lack of additional US government and international orders.
A total of 190 C-17s are contracted for delivery to the USAF as of October 24, 2007. Efforts are underway to add a further 10 C-17s to a funding/supplemental bill so that production may be extended to 2010 and to allow for further potential FMS purchases to take effect.

No comments: